Reuse unchanged assets
Survey condition, materials, controls support, spare parts and duty before assigning reuse value. Record connections, tags, software versions, calibration records and the preservation method.
Compare asset reuse, destination readiness, uncovered downtime and restart costs before committing to a food factory move.

Start with the business outcome
DPS can coordinate a relocation as an integrated production-system project: review assets, prepare the receiving site, manage dismantling and installation interfaces, and organize commissioning. The owner’s value comes from selecting a viable alternative and controlling transition cost, rather than assuming that moving the same equipment creates new recurring profit.
Confirm who owns rigging, transport, lifting plans, OEM preservation, insurance, destination construction, permits and product release. DPS’s published integration scope is not a blanket commitment to supply every specialist trade or jurisdictional approval.

Survey condition, materials, controls support, spare parts and duty before assigning reuse value. Record connections, tags, software versions, calibration records and the preservation method.
Identify work that is safer or less disruptive while equipment is disconnected. Price seals, valves, instruments, insulation and controls changes alongside the new site interfaces.
Compare new equipment where condition, cleanability, capacity, footprint or unsupported controls make relocation unattractive. Include lead time and the receiving process’s readiness.
The receiving facility must be ready before the move removes productive equipment from the old plant.
Use an agreed asset register, isolation sequence and OEM preservation instructions for specialist equipment.
Plan utilities testing, controls restoration, dry / wet checks, qualified trials and the owner’s product-release process.
Swipe horizontally to compare all columns ↔
| System | Operating duty | Relevant DPS guide | Confirm before purchase |
|---|---|---|---|
| Process engineering | Turn a measured operating gap into an agreed design basis. | Process engineering ↗ | Representative products, drawings, duty and required acceptance evidence. |
| Capital alternatives | Compare reuse, renewal and staged transfer on matched scope. | Capital planning ↗ | Owner’s cash constraints, alternative assumptions and downside exposure. |
| Field installation and integration | Coordinate retained assets and specialist OEM packages. | Installation & integration ↗ | Mechanical, electrical, utilities, isolation, testing and handover scope. |
| Automation and instrumentation | Recipes, permissives, sequence visibility and agreed interfaces. | Automation & controls ↗ | I/O, operating states, alarm handling, backup, training and ownership. |
The figures below are a hypothetical counterfactual, not supplier price benchmarks. Keep destination work common only when the scope is genuinely identical. The comparison is separate from the annual ROI calculator.
Swipe horizontally to compare all columns ↔
| Cost or decision | Reuse / move | Selected new packages |
|---|---|---|
| Defined equipment / move scope | 500,000 | 850,000 |
| Destination work | 200,000 | 200,000 |
| 15% capital contingency | 105,000 | 157,500 |
| Uncovered transition contribution loss | 120,000 | 60,000 |
| Working capital | 80,000 | 80,000 |
| Initial transition cash | 1,005,000 | 1,347,500 |
| Difference | Base alternative | 342,500 more initial cash |
| Future operating costs / life | Verify condition and supportability | Verify savings, service costs and useful life; no values assumed here |
Swipe horizontally to compare all columns ↔
| Observed condition | Measure before design | DPS / team decision | Economic basis |
|---|---|---|---|
| Unready receiving site | Record civil, utility, equipment and permit readiness by area. | Set a destination-ready gate before equipment removal. | One-time uncovered downtime and temporary-service exposure. |
| Unknown retained condition | Inspect assets and controls support against the new duty. | Compare reuse, refurbishment and replacement. | All-in alternative cost and future maintenance; do not use book value as a cash saving. |
| Disruption to customers | Model inventory cover, external production and shipping. | Coordinate production transfer with the commercial plan. | Uncovered lost contribution plus actual temporary costs, without double-counting. |
| Slow restart | Assign utilities, controls, trials and release ownership. | Plan integrated tests, training and spare parts. | One-time ramp exposure; recurring benefits require a separate verified improvement. |
Use a condition and duty survey to identify reusable assets, required refurbishment and new site interfaces. Build a matched-scope estimate that includes both sites and the transition period.
New packages can sometimes be installed and tested while the old plant runs, subject to site readiness and available capital. Verify product trials, OEM lead times and overlap costs.
Compare proposals with the same product duty, supplier boundaries and acceptance basis. The amount below is a transparent planning example, not a market price range, supplier estimate or DPS quotation.
| Cost bucket | Assumed amount |
|---|---|
| Asset survey and relocation engineering | $65,000 |
| Dismantling, preservation and transport allowance | $125,000 |
| Reinstallation and destination connections | $180,000 |
| Controls restoration / interface work | $55,000 |
| Commissioning and product-trial scope | $55,000 |
| Training / documentation / closeout | $20,000 |
| Defined project scope | $500,000 |
| Separate site / facility additions | $200,000 |
| Capital contingency (15%) | $105,000 |
| Separate one-time startup / shutdown cost | $120,000 |
| Incremental working capital | $80,000 |
| Total initial cash | $1,005,000 |
The defined scope assumes applicable freight, procurement charges and taxes are included in the owner’s estimate. Add missing civil, land / shell, OEM, environmental, validation and permitting costs explicitly. Site and field conditions, duty, production access and quoted supplier scope determine actual price. Financing is excluded.
This transition-only default deliberately assigns zero recurring benefit. Defined move scope $500,000 + receiving-site work $200,000 + 15% contingency $105,000 + separate transition exposure $120,000 + working capital $80,000 = $1,005,000 initial cash. A mandatory move is not justified by inventing extra annual sales. Use the annual model only for separately evidenced differences in future operating economics; compare required relocation alternatives on total cost and risk.
Calculated from these assumptions: steady annual net benefit $0; year-one net cash $0; cash payback Beyond 5 years; five-year NPV at 10% is −$1,005,000. Change the assumptions below to test a different case.
Replace the illustrative inputs with your own measured or quoted values. The five-year pre-tax model uses good kilograms, demand-capped contribution and separately verified baseline savings; it is not a project quotation.
All defaults are illustrative. The relocation default costs the transition and assumes zero recurring benefit; it therefore has no operating payback. Add only separately evidenced future operating differences. For a new operation, set baseline savings to zero and enter every additional operating and capital cost.
Includes contingency, startup and working capital
Incremental operating cash before tax
Includes year-one ramp assumption
At 10% annual discount
Net annual benefit ÷ initial cash
Net cumulative gain ÷ initial cash
Modeled incremental sales: 0 kg/year at $0.00/kg contribution. The base case does not recover the required discounted return within five years. Year-one net cash: $0.
Realization needed for the target operating payback
Not feasible
Demand, time, contribution or other cash benefits cannot meet the 5-year target under these assumptions.
CSV export is local. No inputs are submitted.
Swipe the chart to compare all five years ↔
Swipe horizontally to compare all columns ↔
| Year | Net cash | Cumulative cash | Discounted cash |
|---|---|---|---|
| Initial | −$1,005,000 | −$1,005,000 | −$1,005,000 |
| Year 1 | $0 | −$1,005,000 | $0 |
| Year 2 | $0 | −$1,005,000 | $0 |
| Year 3 | $0 | −$1,005,000 | $0 |
| Year 4 | $0 | −$1,005,000 | $0 |
| Year 5 | $0 | −$1,005,000 | $0 |
Swipe horizontally to compare all columns ↔
| Case | Annual benefit | NPV | Cash payback |
|---|---|---|---|
| Downside | $0 | −$1,166,000 | Beyond 5 years |
| Base | $0 | −$1,005,000 | Beyond 5 years |
| Upside | $0 | −$1,005,000 | Beyond 5 years |
Downside: installed and site costs +20%, realization ×0.75 and unit contribution reduced by 20% of its absolute value. Upside: realization ×1.15, capped at 100%, and unit contribution improved by 10% of its absolute value. The demand ceiling still applies.
Initial cash = (defined project scope + site additions) × (1 + contingency) + separate startup / shutdown cost + working capital. Contingency is conservatively treated as spent initially.
Sold incremental kg = min(days × recovered hours/day × constrained good kg/hour × realization, incremental demand). Contribution = sold incremental kg × (net price − incremental variable cost). New-volume labor, energy and packaging belong in that variable cost.
Baseline material benefit uses the verified percentage of actual purchases avoided at unchanged accepted baseline output. It is not a direct subtraction of two loss rates. Count a recovered kilogram once, either as its applicable cash saving or as incremental contribution.
Net annual benefit = contribution + independently realized baseline cash savings − added fixed operating cost. Year one scales gross benefits by the ramp factor while paying the full added fixed operating cost. Do not also count the same launch loss in the one-time startup amount.
Cash ROI = net annual benefit / initial cash. Five-year net ROI = (five-year cash inflows − initial cash) / initial cash. NPV = −initial cash + Σ cash flow(t)/(1 + discount rate)^t. Payback uses annual cash with linear interpolation within the recovery year. The threshold solver excludes terminal working-capital recovery.
This is a five-year screening horizon, not an asset’s entire life. No tax, debt, depreciation, grants, escalation, asset resale or additional replacement capital is modeled. Include recurring service costs in operating expense and use a detailed monthly budget for formal capital approval.
Compare uncovered production hours after feasible inventory or external-production cover. Use lost contribution, not revenue. Include the extra cost of the shorter plan.
Use representative products, measured constraints and a documented utility / cleaning envelope. Assign each supplier and owner interface.
Plan FAT / SAT, instruments, recipes, permissives, quality checks and upstream / downstream handshakes as appropriate to the scope.
After stabilization, compare matched products and operating conditions. Reconcile extra output with sales, and baseline savings with actual purchases, bills and payroll.

Published scope / project context
DPS publishes project delivery, process engineering, installation, controls and utility-related scope. The published case overview demonstrates project context; no measured ROI, price or performance for the hypothetical example below is attributed to a DPS customer.
Swipe horizontally to compare all columns ↔
| Decision | Targeted intervention | Broader replacement / new operation |
|---|---|---|
| Constraint | A measured gap can be corrected within retained assets. | The verified operating envelope cannot meet product, demand or reliability needs. |
| Cost scope | Include engineering, interfaces, shutdown, commissioning and retained-asset risk. | Include all new systems, site / facility work, OEMs, utilities, ramp and working capital. |
| Benefit | Only incremental contribution and genuinely avoided costs versus the current operation. | Demand-supported contribution less the full additional operating cost versus the agreed alternative. |
| Acceptance | Verify the changed duty and its effect on the complete line. | Verify the integrated new train and the owner’s readiness to operate. |
Prepare the information below, export the assumptions you have modeled, and discuss the unknowns with DPS. An unmeasured input is a question to resolve, not a reason to invent precision.
Checklist and model data stay in this browser until you choose to share them.
The DPS manufacturing-scenarios overview frames relocation around equipment condition, destination readiness and restart compatibility. This page develops those decisions into a transparent transition-cost comparison; its numbers are original illustrative assumptions.
Guide assumptions reviewed on 26 October 2026. Qualified site / product teams establish regulatory and food-safety requirements; this guide does not prescribe a validated process.

Compare expanding an existing food plant with a new facility using site fit, infrastructure, production disruption, delivered capacity and investment timing.

See what separates equipment purchase cost from total installed cost: package boundaries, utilities, installation, controls, testing and exclusions.

Build a food plant interface matrix covering building, process, utilities and controls, using a four-system integration lesson and explicit owners.