Process and packaging demand
Record the actual flow, pressure, quality and event pattern of each user. Short simultaneous requests can cause local problems that average compressor output conceals.
Evaluate compressors, receivers, drying, distribution, quality and real equipment demand as one operating system.

Start with the business outcome
Pressure complaints do not automatically justify another compressor. DPS can coordinate source, storage, treatment, distribution, controls and equipment interfaces with qualified specialists. Compare metered operation and the actual user requirement. A leak or control correction can reduce purchased energy, but it does not establish extra accepted food output without a separate production case.
The responsible product / equipment teams specify air quality and any product-contact requirements. Qualified specialists establish receiver / pressure systems, electrical work and treatment packages. No generic air-quality class or universal leak saving is assigned to the plant.

Record the actual flow, pressure, quality and event pattern of each user. Short simultaneous requests can cause local problems that average compressor output conceals.
Check controls, load states, storage, treatment and available duty together. A receiver cannot create source energy or cure an unsuitable air-quality basis.
Measure local pressure loss and nonproductive demand. Repair priorities should follow measured loss and the ability to isolate / verify work, not only audible leakage.
Meter the system and map equipment requests across production and nonproduction states.
Compare verified avoidable loss, local restrictions and appropriate operating controls.
Specify a larger package only after real present / future duty is established.
Swipe horizontally to compare all columns ↔
| System | Operating duty | Relevant DPS guide | Confirm before purchase |
|---|---|---|---|
| Utility supply and return | Meet the duty where the process actually uses it. | Utility infrastructure ↗ | Peak overlap, recovery, quality, point-of-use conditions and isolation. |
| Compressor / receiver / treatment packages | Meet required air quantity, quality and control duty. | Process engineering ↗ | Qualified package supply, pressure / electrical work and owner quality basis. |
| Instrumentation and controls | Execute the agreed sequence and record meaningful equipment states. | Automation & controls ↗ | I/O, alarms, recipe authority, backups and acceptance tests. |
| OEM and field interfaces | Connect the selected equipment to the existing operating train. | Installation & integration ↗ | Mechanical, electrical, software, site access and integrated acceptance. |
Evaluate individual components and how they interact with demand before approving capacity.
Swipe horizontally to compare all columns ↔
| Decision | What to compare | Acceptance evidence |
|---|---|---|
| Source capacity | Actual loaded power, control and concurrent useful duty | Required source response and measured energy. |
| Storage / treatment | Events, quality basis, dryer and receiver duty | Required conditions without unsuitable pressure / quality assumptions. |
| Distribution / demand | Local restrictions and avoidable nonproductive flow | Verified user condition and actual energy-bill change. |
Swipe horizontally to compare all columns ↔
| Observed condition | Measure before design | DPS / team decision | Economic basis |
|---|---|---|---|
| Pressure drop at a user | Trend local event and source state. | Separate source, storage and distribution limits. | Required operating condition; extra sales remain conditional. |
| Nonproductive air use | Measure nonproduction / matched demand. | Correct verified avoidable loss. | Actual purchased-energy reduction. |
| Poor source control | Review power and loading sequence. | Compare suitable control changes. | Metered baseline cost after service expense. |
| Capacity proposal | Build actual concurrent demand. | Compare correction and expansion. | Full source / treatment / distribution alternatives. |
Start with user pressure and source power / load trends, then distinguish avoidable demand, distribution loss and insufficient source duty. Preserve adequate packages and define isolated work.
Compile equipment demand, concurrent events and required air quality before source / receiver / dryer selection. Include distribution, electrical, controls and annual service costs.
Compare proposals with the same product duty, supplier boundaries and acceptance basis. The amount below is a transparent planning example, not a market price range, supplier estimate or DPS quotation.
| Cost bucket | Assumed amount |
|---|---|
| Application engineering and supplier duty review | $19,000 |
| Defined equipment / instrumentation components | $69,000 |
| Mechanical and electrical field installation | $35,000 |
| Controls and interface development | $21,000 |
| Commissioning / agreed acceptance support | $10,000 |
| Training, documentation and handover | $6,000 |
| Defined project scope | $160,000 |
| Separate site / facility additions | $20,000 |
| Capital contingency (15%) | $27,000 |
| Separate one-time startup / shutdown cost | $10,000 |
| Incremental working capital | $0 |
| Total initial cash | $217,000 |
The defined scope assumes applicable freight, procurement charges and taxes are included in the owner’s estimate. Add missing civil, land / shell, OEM, environmental, validation and permitting costs explicitly. Site and field conditions, duty, production access and quoted supplier scope determine actual price. Financing is excluded.
Hypothetical screening case: 250 days × 0 equivalent useful hour/day × 0 accepted kg/h × 0% realization, capped at 0 kg incremental demand, gives 0 additional sold kg/year. Net price $0/kg less incremental variable cost $0/kg gives $0/kg contribution. Verified baseline purchase savings are $0, realized payroll savings $0, energy $40,000, cleaning resources $0 and maintenance $5,000 per year. Deduct $8,000 additional annual fixed cost. The default is energy-led and assumes no additional product sales. It does not convert a pressure improvement or leak estimate directly into production revenue.
Calculated from these assumptions: steady annual net benefit $37,000; year-one net cash $28,000; cash payback Beyond 5 years; five-year NPV at 10% is −$84,923. Change the assumptions below to test a different case.
Replace the illustrative inputs with your own measured or quoted values. The five-year pre-tax model uses good kilograms, demand-capped contribution and separately verified baseline savings; it is not a project quotation.
All defaults are illustrative. The default case is an operating-plant improvement, not a greenfield quote. For a new operation, set baseline savings to zero and enter every additional operating and capital cost.
Includes contingency, startup and working capital
Incremental operating cash before tax
Includes year-one ramp assumption
At 10% annual discount
Net annual benefit ÷ initial cash
Net cumulative gain ÷ initial cash
Modeled incremental sales: 0 kg/year at $0.00/kg contribution. The base case does not recover the required discounted return within five years. Year-one net cash: $28,000.
Realization needed for the target operating payback
Not feasible
Demand, time, contribution or other cash benefits cannot meet the 4-year target under these assumptions.
CSV export is local. No inputs are submitted.
Swipe the chart to compare all five years ↔
Swipe horizontally to compare all columns ↔
| Year | Net cash | Cumulative cash | Discounted cash |
|---|---|---|---|
| Initial | −$217,000 | −$217,000 | −$217,000 |
| Year 1 | $28,000 | −$189,000 | $25,455 |
| Year 2 | $37,000 | −$152,000 | $30,579 |
| Year 3 | $37,000 | −$115,000 | $27,799 |
| Year 4 | $37,000 | −$78,000 | $25,271 |
| Year 5 | $37,000 | −$41,000 | $22,974 |
Swipe horizontally to compare all columns ↔
| Case | Annual benefit | NPV | Cash payback |
|---|---|---|---|
| Downside | $37,000 | −$126,323 | Beyond 5 years |
| Base | $37,000 | −$84,923 | Beyond 5 years |
| Upside | $37,000 | −$84,923 | Beyond 5 years |
Downside: installed and site costs +20%, realization ×0.75 and unit contribution reduced by 20% of its absolute value. Upside: realization ×1.15, capped at 100%, and unit contribution improved by 10% of its absolute value. The demand ceiling still applies.
Initial cash = (defined project scope + site additions) × (1 + contingency) + separate startup / shutdown cost + working capital. Contingency is conservatively treated as spent initially.
Sold incremental kg = min(days × recovered hours/day × constrained good kg/hour × realization, incremental demand). Contribution = sold incremental kg × (net price − incremental variable cost). New-volume labor, energy and packaging belong in that variable cost.
Baseline material benefit uses the verified percentage of actual purchases avoided at unchanged accepted baseline output. It is not a direct subtraction of two loss rates. Count a recovered kilogram once, either as its applicable cash saving or as incremental contribution.
Net annual benefit = contribution + independently realized baseline cash savings − added fixed operating cost. Year one scales gross benefits by the ramp factor while paying the full added fixed operating cost. Do not also count the same launch loss in the one-time startup amount.
Cash ROI = net annual benefit / initial cash. Five-year net ROI = (five-year cash inflows − initial cash) / initial cash. NPV = −initial cash + Σ cash flow(t)/(1 + discount rate)^t. Payback uses annual cash with linear interpolation within the recovery year. The threshold solver excludes terminal working-capital recovery.
This is a five-year screening horizon, not an asset’s entire life. No tax, debt, depreciation, grants, escalation, asset resale or additional replacement capital is modeled. Include recurring service costs in operating expense and use a detailed monthly budget for formal capital approval.
These hypothetical defaults give $40,000 gross annual baseline electricity savings, matching the main example. The 25% reduction is an assumed measured project result to replace, not an industry guarantee. Added service is in the main $8,000 annual fixed cost.
Use representative products, measured constraints and a documented utility / cleaning envelope. Assign each supplier and owner interface.
Plan FAT / SAT, instruments, recipes, permissives, quality checks and upstream / downstream handshakes as appropriate to the scope.
After stabilization, compare matched products and operating conditions. Reconcile extra output with sales, and baseline savings with actual purchases, bills and payroll.

Published scope / project context
DPS publishes process engineering, configured equipment, controls and installation / integration services. The source links establish relevant scope. The amounts, time changes, resource reductions and returns here are original hypothetical inputs, not achieved DPS customer results.
Swipe horizontally to compare all columns ↔
| Decision | Targeted intervention | Broader replacement / new operation |
|---|---|---|
| Constraint | A measured gap can be corrected within retained assets. | The verified operating envelope cannot meet product, demand or reliability needs. |
| Cost scope | Include engineering, interfaces, shutdown, commissioning and retained-asset risk. | Include all new systems, site / facility work, OEMs, utilities, ramp and working capital. |
| Benefit | Only incremental contribution and genuinely avoided costs versus the current operation. | Demand-supported contribution less the full additional operating cost versus the agreed alternative. |
| Acceptance | Verify the changed duty and its effect on the complete line. | Verify the integrated new train and the owner’s readiness to operate. |
Prepare the information below, export the assumptions you have modeled, and discuss the unknowns with DPS. An unmeasured input is a question to resolve, not a reason to invent precision.
Checklist and model data stay in this browser until you choose to share them.
Natural Resources Canada describes assessment of compressors, distribution and operating demand as a system. Its assessment guidance is not a prediction of savings or a food-contact air specification for this project.
Guide assumptions reviewed on 26 October 2026. Qualified site / product teams establish regulatory and food-safety requirements; this guide does not prescribe a validated process.

Define a food plant utility design basis using operating events, simultaneous peaks, supply conditions, future capacity and clear package interfaces.

Confirm utility availability before buying land: required conditions, provider evidence, connection scope, upgrade responsibilities and decision deadlines.

Compare utility peak capacity, sequencing and buffers using a timed load model, DPS CIP interfaces and a reported retrofit case with staged tie-ins.